This year, the Andrews Labor Government have deliberately failed to publish the State Capital Program (Budget Paper 4), which highlight the budget blowouts and timeline blowouts on capital infrastructure projects.
Under Daniel Andrews there has been more than $25.48 billion in waste and cost blow outs (that Victorians know about), including:
North East Link
Promised: $5 billion
Last Update: $15.79 billion
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $10.79 billion
CURRENT BUDGET BLOWOUT: Withheld
West Gate Tunnel
Promised: $500 million
Last Update: $6.7 billion
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $6.2 billion
CURRENT BUDGET BLOWOUT: Withheld
Level Crossing Removals
Promised: $5 billion
Last Update: $8.3 billion (Victorian Auditor-General)
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $3.3 billion
CURRENT BUDGET BLOWOUT: Withheld
Metro Tunnel
Promised: $9 billion
Last Update: $11 billion
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $2 billion
CURRENT BUDGET BLOWOUT: Withheld
East West Link
Promised: $0 to cancel
Cost: $1.3 billion to cancel it
LAST REPORTED BLOWOUT: $1.3 billion
Victorian Heart Hospital
Promised: $150 million
Last Update: $564 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $414 million
CURRENT BUDGET BLOWOUT: Withheld
Cranbourne Line Duplication
Promised: $750 million
Parliamentary Budget Office: $1001.2m
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $251.2 million
CURRENT BUDGET BLOWOUT: Withheld
Caulfield to Dandenong conventional signalling upgrade
Promised: $360m
Last Update: $608.28m
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $248.28 million
CURRENT BUDGET BLOWOUT: Withheld
Mordialloc Freeway
Promised: $300m
Last Update: $523m
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $223 million
CURRENT BUDGET BLOWOUT: Withheld
Cranbourne Pakenham Line Upgrade
Promised: $407.1m
Last Update: $597m
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $189.9 million
CURRENT BUDGET BLOWOUT: Withheld
Hurstbridge Line Upgrade Stage 2
Promised: $530 million
Parliamentary Budget Office: $698.8 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $168.8 million
CURRENT BUDGET BLOWOUT: Withheld
Royal Victorian Eye and Ear Hospital redevelopment
Promised: $201 million
Last Update: $274.6 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $73.6 million
CURRENT BUDGET BLOWOUT: Withheld
Seaford (Frankston Line) Stabling Project
Promised: $187.4 million
Last Update: $236.7 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $49.3 million
CURRENT BUDGET BLOWOUT: Withheld
Hoddle Street Upgrade
Promised: $60 million
Last Update: $108.6 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $48.6 million
CURRENT BUDGET BLOWOUT: Withheld
Plenty Road Upgrade – Stage 2
Promised: $103.4 million
Last Update: $143.4 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $40 million
CURRENT BUDGET BLOWOUT: Withheld
Casey Hospital Expansion
Promised: $106.3 million
Last Update: $139.8 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $33.5 million
CURRENT BUDGET BLOWOUT: Withheld
Yan Yean Road Upgrade
Promised: $95 million
Last Update: $126 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $31 million
CURRENT BUDGET BLOWOUT: Withheld
Ballarat Line Upgrade
Promised: $516.7 million
Last Update: $549.5 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $32.8 million
CURRENT BUDGET BLOWOUT: Withheld
Infringement Management and Services Reform Project (Fines Victoria)
Promised: $43 million and delivery December 2017
Last Update: $63.3 million and delivery June 2020
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $20.3 million
CURRENT BUDGET BLOWOUT: Withheld
Optimising Transport Network Performance – Congestion Package
Promised: $82.4 million
Last Update: $102.5 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $20.1 million
CURRENT BUDGET BLOWOUT: Withheld
Frankston Station Upgrade
Promised: $50 million
Last Update: $61.8 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $11.8 million
CURRENT BUDGET BLOWOUT: Withheld
V/Line Fleet Maintenance
Promised: $12.5 million
Last Update: $23 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $10.5 million
CURRENT BUDGET BLOWOUT: Withheld
Hallam Road Upgrade
Promised: $45.014 million
Last Update: $53.514 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $8.5 million
CURRENT BUDGET BLOWOUT: Withheld
Huntingdale Station Carpark
Promised: $4.8 million
Last Update: $11.5 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $6.7 million
CURRENT BUDGET BLOWOUT: Withheld
Mount Buller Water Storage
Promised: $2.06 million
Last Update: $8.25 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $6.19 million
CURRENT BUDGET BLOWOUT: Withheld
Thomas Embling Hospital expansion
Promised: $19.3 million
Last Update: $23.3 million
20/21 Budget: Withheld
LAST REPORTED BLOWOUT: $4 million
CURRENT BUDGET BLOWOUT: Withheld